1. Weather permitting, this coming Friday we are drilling the piers for the worship center expansion.
2. Next week, underground work for the worship center will take place (running cable/electricity/etc conduit).
3. Which would mean we are pouring concrete the following week (week of May 3).
4. Steel should go up May 24.
Also, the week of May 17, less than 30 days away, there will be significant demo work on the first floor. By that I mean the admin office area is getting taken out, the 1st floor bathrooms will be taken out, 1st floor carpet will be ripped up, etc. We will have temporary, but very nice bathroom facilities outside (like at Redstone) and the upstairs bathrooms.